Scope & Timeline

The program is delivered through eight parallel workstreams over twelve months. Several streams overlap deliberately to compress the schedule while maintaining a single point of accountability.

Major Work StreamKey OutputsDuration
Core LLM PlatformOracle AI integration + Widget3 months
Microsoft 365 IntegrationOutlook, Teams, Word, SharePoint6 months (overlapping)
Salesforce IntegrationClient portal + CRM dashboards6 months (overlapping)
Vendor Integrations20 major legal software providers9 months (rolling release)
Developer SandboxSDK + APIs + Compliance Pipeline4 months
MarketplaceSales and Licensing Front End3 months
Security & ComplianceSOC 2 / ISO alignmentContinuous
Management & UXPM + Design Iterations12 months continuous
MonthActivity
1–2Discovery + Architecture Design
3–4Core Platform Development
4–6Microsoft 365 and Salesforce Foundation
6–9Developer Sandbox + First Vendor Integrations
9–10Marketplace Implementation
10–11Remaining Vendor Integrations
12Testing & Go-Live
timeline
  title Integrated 12-month delivery timeline
  Months 1-2 : Discovery + Architecture Design
  Months 3-4 : Core Platform Development
  Months 4-6 : Microsoft 365 + Salesforce Foundation
  Months 6-9 : Developer Sandbox + First Vendor Integrations
  Months 9-10 : Marketplace Implementation
  Months 10-11 : Remaining Vendor Integrations
  Month 12 : Testing & Go-Live + Pilot Launch

The integrated schedule overlaps the Microsoft 365, Salesforce, and rolling vendor streams to compress twelve months down to a single Month-12 go-live and pilot launch.

  • Overlapping streams. Microsoft 365 and Salesforce foundations run in parallel; vendor integrations roll out continuously from Month 6.
  • Rolling vendor releases. The 20 vendor integrations follow a rolling-release model across nine months rather than a single big-bang launch.
  • Continuous workstreams. Security & compliance and PM/UX run continuously across the full year.
  • Pilot launch. Pilot law firms go live at Month 12 (see Governance & Next Steps).

Budget for each workstream is detailed in Cost & Investment.